Long-lead electrical equipment now takes years to arrive. Set your contract below and see the balloon, the schedule and the contingency. Outputs are ranges where their inputs are ranges, and every output shows its basis: a cited figure, a figure derived from cited figures, or a Sustainable Gaps assumption labeled as one. The data is the Sustainable Gaps dataset. Hover or tap any number for its basis and sources.
The equipment queue reprices your job whether you plan for it or not. Priced in precon, the cost is visible and bounded. Found later, it arrives as change orders and rented power, and on Sustainable Gaps assumptions it costs a multiple [e].
A $30M substation scope priced today comes to $40M to $43M if it is delivered in 2031, five years out [e]. That range includes Sustainable Gaps assumptions for longer-schedule overhead and a queue and bridge allowance. Equipment and labor price escalation alone, at their recent pace, gives $36M to $39M by 2031 [e] [16][17]. The calculator below gives $40M to $43M for a 2028 start. At its default 2026 start the equipment arrives sooner, delivery comes in about 2029, and the total is $36M to $38M [e]. The longer the queue, the longer the job sits exposed to those prices.
The queue is measured in years
A power transformer took about 50 weeks to arrive in 2021. By 2024 the average was 120 weeks, and in Q2 2025 it was 128 [1][2]. That is the newest survey average in open sources. Quotes from mid-2026 run from 65 weeks for a 5 to 25 MVA unit to 256 weeks. The top of that range comes from one maker's lines on a manufacturer representative's sheet, which prints 59 months for a 10 to 30 MVA unit and 43 to 44 months for 20 to 120 MVA [14]. Generator step-up units averaged 143 weeks in 2024 and passed 160 weeks by Q1 2026 [4]. High-voltage breakers went from 77 weeks in 2023 to 125 weeks in the second half of 2025 [4].
Small units have come back. Distribution transformers took 2 to 3 months in 2019 and 2020 and about a year in 2022 and 2023 [6][9]. The wait reached about two years in 2024 and fell to about 30 weeks by Q2 2025 [5]. The same sheet listed one maker's three-phase pad-mounts at 14 to 28 weeks in July 2026 [14]. Switchgear averaged 44 weeks in Q2 2025 [2], and 2026 quotes for 5 to 15 kV gear run 20 to 80 weeks, with 38 kV gear at 56 to 120 weeks [14]. The gear that energizes a substation has not come back.
Prices went up and stayed up
The producer price index for the transformer manufacturing industry stood 88% above its 2019 average in September 2026 (preliminary). The switchgear industry index stood 95% above [16]. The transformer index rose 4% in July 2026 alone, also a preliminary month. Distribution lead times fell from about two years in 2024 to about 30 weeks by Q2 2025, and the price index gave none of the increase back.
Relief has a date, and some dates move
Imports were estimated to be about 80% of U.S. power transformer supply in 2025 (Wood Mackenzie, August 2025) [28]. In 2027 and 2028, 12 of 29 announced U.S. plants and expansions are due to ship, with $1.9B in disclosed investment [23]. Some dates have moved. The company behind a large-transformer plant announced for early 2026 said in June 2025 that it expected its first units in early 2027 [23]. A distribution plant due in the first half of 2026 was canceled in May 2025 [23]. In August 2026 an executive order authorized DOE to bar transactions in bulk-power equipment, including substation transformers and high-voltage breakers, linked to covered foreign entities, once DOE determines the transaction poses an undue or unacceptable risk [24]. The calculator holds today's queue flat through 2027 [e].
Bridge power got more expensive this year
One megawatt of diesel generation running for a month burns about 51,100 gallons, at a full-load rate of 0.07 gallons per kWh, a Sustainable Gaps assumption. Retail diesel averaged $3.52 in January 2026 and $6.35 in the last week of October [18]. Fuel alone is now $316K to $325K per MW-month, and $337K to $386K with an assumed rental share [e]. Data centers were 2% of Aggreko's group revenue in 2021 and 11% in 2025, and 19% of its net revenue in the first half of 2026 [20]. The usual escape, a gas turbine, has its own queue. GE Vernova's gas backlog and reserved slots grew from 62 GW to 122 GW in the year to Q3 2026 [19].
What it costs on a $30M job
On Sustainable Gaps assumptions [e], an early equipment buy and a re-sequenced schedule cost $0.8M to $1.5M when they are designed in. The same two items cost $2.9M to $5.0M as change orders, about 3.5 times as much. If the customer's load shows up on the original date and 5 MW of power has to be rented for a year, the change-order bill is $23.1M to $28.2M [e].
What to do at bid
Name the factory slot for every long-lead item before you name a finish date. Release the order at 30% design when the owner agrees to carry the design-change risk. Tie equipment price to a published index in the contract. Price bridge power as a dated option with a purchase order for the permanent fix and an end date. Cap bridge power spending near 60 to 70% of what the permanent fix costs, a Sustainable Gaps assumption [e]. Temporary power can run for years: two federal task orders for temporary generation at two Puerto Rico plants reached $1.49B between 2023 and 2026 [22].
The calculator below runs these numbers against your contract. Where a number is a Sustainable Gaps assumption, it says so.
Weeks from order to delivery. Dots are the figure the calculator uses: the survey average for that year where one exists, otherwise a reported or derived value. Whiskers span the dated quotes and survey figures selected for each class and year, and each whisker's hover note names them. The dashed whisker at 2026 is 38 kV switchgear. Hollow dots right of the shaded line are Sustainable Gaps projections [e].
Solid dot: a survey average for that year (SOURCED). Ring on the solid line: a reported wait that is not a survey average (distribution 2024, a two-year wait reported by CRS, SOURCED), or a DERIVED value. A derived value is the median of dated observations, a 2026 value carried forward from the newest survey average in open sources (Q2 2025) for distribution transformers, power transformers and switchgear, or the 2026 floor for large units (GSUs above 160 weeks by Q1 2026). The Q2 2025 switchgear average does not state a voltage class.
Sources [1][2][3][4][5][6][7][8][9][10][11][12][13][14][15][23][29] in the source list. Lead-time data as of 2026-07-30. Newest quote sheet: 2026-07-30. Newest survey figure: Wood Mackenzie GSU, Q1 2026 (reported 2026-07-09). The newest Wood Mackenzie averages in open sources for power transformers, distribution transformers and switchgear are Q2 2025.
Producer price indexes for the two manufacturing industries, percent above the 2019 average. Lead times for small units came down after 2024. These lines did not. The last plotted month, September 2026, is preliminary.
Source [16]: BLS series PCU335311335311 and PCU335313335313, retrieved 2026-10-31. Data through 2026-09. Months from 2026-06 on are preliminary.
Transformer, electrical steel and switchgear plants announced 2022 to 2026, counted by current online year. Each block is one project. 12 of the 29 projects are due in 2027 or 2028. Unit capacity is mostly not disclosed.
Not shown: a Canadian plant, GE Vernova's purchase of Prolec GE (an ownership change) and Hubbell's expansion of existing plants (no site, amount or date stated). Canceled: Cleveland-Cliffs, Weirton, WV (announced 2024-07-22, due 2026).
Source [23]: company, state and trade-press sources, one or more per project. Status read 2026-10-31. Dollar totals count only projects that disclosed an amount.
The calculator
$5M to $200M
Engineered electrical gear as % of contract. Reference case: 45%.
The four weights are scaled to total 100%. The mix drives your queue length and contingency.
Later starts meet shorter projected queues [e] and higher prices.
Months after award. Reference schedule: month 24.
At these inputs the job can energize at month 40. To make month 24, the order had to go out 12 months before award. At the 128-week lead time used here, the date is met only if the order was placed or a factory slot held before award, by the owner or by the winning firm, or if a quote at award is at least 12 months shorter.
+21.3 to 27.2% on your $30M by about 2029 delivery
Priced today: $30M. Queue 128 weeks. Energizes at month 40
What each day of delay adds to the same equipment order, at the yearly re-quote rate spread per day. Quotes hold 30 to 60 days, then re-price
2.7 to 5.0% of contract, by class mix and start year. Released back if the risk clears
5 MW for 12 months at $337K to $386K per MW-month at October 2026 diesel. Priced as an option in precon, or rented at spot rates when the date is missed
Crews idle about 20 months between civil completion and gear arrival, at $125K a month
On the reference job, and on Sustainable Gaps assumptions [e], the same two line items cost $0.8M to $1.5M when priced in precon and $2.9M to $5.0M as change orders, about 3.5 times as much.
The plan for your contract date, month 24, against the schedule your inputs produce. Every bar that shifts right is an operating cost.
SOURCED Read from a dated, cited source.
DERIVED Computed from sourced figures. The computation is stated.
JUDGMENT Sustainable Gaps assumption, stated, with the next re-check by 2027-02-01. No source carries it.
[e] Estimate or forecast. Assumptions stated, never presented as measured fact.
Outputs are ranges where their inputs are ranges, and each carries the weakest label among its inputs. Hover or tap any number for its computation note and numbered citations. The full source list is in Assumptions and sources. Dotted-underlined terms carry plain-English definitions.